1

Application

Received 15th March 2005

Application by Epic Energy for revocation.

2

Submissions on application

Submissions have closed.

3

Draft recommendation

Draft recommendation released.

4

Submissions on draft recommendation

Submissions on draft recommendation have closed.

5

Final recommendation and decision

The Council's Final recommendation.

6

Outcome & subsequent events

Minister's statement of decision and reasons.

Moomba to Adelaide Gas Pipeline System

Moomba to Adelaide Gas Pipeline System: Application to revoke coverage under National Gas Code.

On 15 March 2005, the National Competition Council received an application from Epic Energy for revocation of coverage under the Gas Pipelines Access (SA) Act 1997 (the Act) and the National Third Party Access Code for Natural Gas Pipelines (the Code) of the transmission pipelines within the Moomba to Adelaide Pipeline System. The system comprises the main transmission pipeline that runs from Moomba to Adelaide in South Australia and laterals (SA:PL1).

The Council released its draft recommendation on 16 November 2005 and its final recommendation on 14 December 2005. The final recommendation was that coverage of the Moomba to Adelaide Pipeline System be revoked.

As required under the Gas Code the Council forwarded its final recommendation to the decision-maker, who in this case was the South Australian Minister for Energy (the Hon. Patrick Conlon MP).

On 16 September 2007, the Hon Patrick Conlon released his decision to revoke coverage of the Moomba to Adelaide Pipeline System.

Copies of the application, the Council's issues paper, draft and final recommendations, public submissions and the Minister's decision are available for download via the relevant tabs on the left-hand panel.